Mill A Removal of Formworks in Progress
Central Electrical Building-Steel Fixing Base Foundation in Progress
Turbine Hall-Hacking of Bored Piles East Side in Progress
Phase 1-Flue Gas Desulfurization Glass Reinforced Pipes-Backfilling in Progress
Mill F-Retaining Wall-South Side Formworks in Progress
Mill D-Retaining Wall-South Side Formworks in Progress
Turbine Hall-Final Preparation Prior to Concreting and Cleaning of Debris
Turbine Hall-West Side Setting up of Spot Lights
F10-Boiler-Hacking of Bored Piles and Removal of Debris
Mill H-Eversendai-Scaffolding Installation in Progress
Flue Gas Duct-Bored Piles Rebar Installation in Progress
Mill H and Mill G-Eversendai-Steel Plates for Crane Base Pads
F4-Boiler-Base Foundation Steel Fixing and Formworks Installation in Progress
F5-Final Preparation Prior to Concreting
F1-Boiler-Stumps Formworks Installation in Progress
F9-Boiler-Base Foundation Steel Fixing and Formworks Installation in Progress
F10-Boiler-Stumps Formworks Installation in Progress