31.03.2012

 Chimney-Steel Fixing Bottom Layer Base Foundation in Progress
 Mill A Removal of Formworks in Progress
 Central Electrical Building-Steel Fixing Base Foundation in Progress
 Turbine Hall-Hacking of Bored Piles East Side in Progress
 Phase 1-Flue Gas Desulfurization Glass Reinforced Pipes-Backfilling in Progress 
 Mill F-Retaining Wall-South Side Formworks in Progress 
 Mill D-Retaining Wall-South Side Formworks in Progress 
 Turbine Hall-Final Preparation Prior to Concreting and Cleaning of Debris
 Turbine Hall-West Side Setting up of Spot Lights 
 F10-Boiler-Hacking of Bored Piles and Removal of Debris
 Mill H-Eversendai-Scaffolding Installation in Progress
Flue Gas Duct-Bored Piles Rebar Installation in Progress 
 Mill H and Mill G-Eversendai-Steel Plates for Crane Base Pads

 F4-Boiler-Base Foundation Steel Fixing and Formworks Installation in Progress
 F5-Final Preparation Prior to Concreting
  F1-Boiler-Stumps Formworks Installation in Progress

 F9-Boiler-Base Foundation Steel Fixing and Formworks Installation in Progress
 F10-Boiler-Stumps Formworks Installation in Progress