24.02.2012

 Installation of First Alstom 400mm Dia Spun Pile for SWFGD GRP Piping Soil Improvement - Absorber Area. 

 Welding Inspection/ Surveillance By Client & Consortium for Spun Pile installation 
(Alstom Scope Spun Piles are Non-Load Bearing - For Soil improvement only) 

 Turbine Hall Foundation - Bottom Layer of Reinforcement and works in progress.

 Boiler Mill Foundation H on right of picture (Cast now Curing) & G on left of picture awaiting installation of bolts.Template frame will move to Mill F on 25/02/12

TMBT Piling & Civil Works Contractor commenced piling for new
 HV Transmission Tower Foundations.

23.02.2012

 Boiler Foundation - preparation of pedestal pour. 
 Turbine Hall Foundation - Cleaning & Dewatering for Reinforcement
 Boiler Foundation Type F10 (East) - Formwork installation
 Boiler Foundation Type F4 (East 1/2) - Final Preparations for Concreting
 Boiler Bunker Steel Structure Pedestals (Mill H South-West) Pre-Pour As-built Survey.
 Boiler Bunker Steel Structure Pedestals (Mill H South-West) Pre-Pour As-built Survey.
 Boiler Bunker Steel Structure Pedestals (Mill H South-West) Pre-Pour As-built Survey.
 Boiler Mill Foundation H (South-West) Curing of Cast Concrete
Boiler Bunker Steel Structure Pedestals (Mill G South-West) Final Rebar Inspection
 Turbine Hall Foundation - (-7.2m EL ) Installation of Bottom layers of Reinforcement
 Turbine Hall Foundation - (-7.2m EL ) Installation of Bottom layers of Reinforcement
 Turbine Hall Foundation - (-7.2m EL ) Installation of Bottom layers of Reinforcement


 Turbine Hall Foundation - (-7.2m EL ) Pile trimming

22.02.2012

Chimney Foundation Bored Piling - 56/56 No. (CMC)

Boiler Foundation Pedestal - Main Steel Structure Bolts (75mm) installed

Boiler Foundation Type F10 (East) - Form work in progress.

Turbine Hall Foundation - Preparation for installation of reinforcement.

Turbine Hall Foundation - Pile trimming

Turbine Hall Foundation - Pile trimming

Turbine Hall Foundation - Condensate Pump Sumps Stage 1 - Deep excavation works

Turbine Hall Foundation - Condensate Pump Sumps Stage 1 - Deep excavation works

Boiler Foundation Bunker Mill Steel Structure Pedestal - Pre Pour Inspections

Boiler Mill Foundation G - Cleaning of reinforcement

Boiler Mill Foundation H - Pre Pour As- built survey of installed bolts

Boiler Mill Foundation H - Final Concrete Pour.

21.02.2012

 Boiler Mill Foundation H Formwork Complete (North)
 Boiler Mill Foundation H & Mill Motor Cantilever Formwork Complete (South)
Boiler F10 Foundation Rebar Complete 
 Boiler Mill Foundation F - Final Construction Joint Preparation
 Turbine Hall Foundation - Pile Trimming & Preparation for installation of Reinforcement.
 Turbine Hall Foundation - Condensate Pump Sump Deep excavation works
 Chimney Foundation - Pile Bore - 55 of 56 No. (CMC)
 Extraction of Boiler F3/7 West Sheet Piles for use in GRP trench under new HV lines 
 Boiler Mill Foundation H - Pre Pour Inspections & Bolt Survey
 Boiler Mill Foundation H - Pre Pour Inspections & Bolt Survey

 Boiler Mill Foundation H - Pre Pour Inspections & Bolt Survey
 Boiler Mill Foundation H - Pre Pour Inspections & Bolt Survey
 Boiler Mill Foundation H - Pre Pour Inspections & Bolt Survey
 Boiler Foundation Type F3 West - Pedestal Rebar Inspection Pre Formwork.
Boiler Foundation Type F6 East - Back Filling  & Compaction

20.02.2012

View From Exisitng MJ1/2/3 -Coal Yard -Laydown Area.

View From MJ1/2/3 -South View -Coal Yard / Laydown Area -GRP Pipes.

View From Exisitng MJ1/2/3 -South View -Turbine Hall/Boiler/Chimney(Bore Pile)/EPCC Office.(Blue Colour Building).

View From Exisitng MJ1/2/3 -South View -Turbine Hall/Boiler/Laydown Area.

View From Existing MJ1/2/3/ -MCWS -Piling In Progress -Spun Pile 600mm dia.

View From Existing MJ1/2/3 -BOP -Water Intake Area -Box Culvert Area.

View From Existing MJ 1/2/3 -View From South.