22.12.2011

Weekly EHS Tool Box Briefing -ALSTOM/CMC/MCB/GIGA/SINOHYDRO/MURRAY ROBERT/ECONPILE.

Boring To Pile # HN41-1200mm dia. -Chimney -BOP -EconPile.

Excavation To Fabric Filter Area.

Fabric Filter -Installation Of Steel Reinforcement -Pile Cap.

Sheet Piling -Coffer Dam -F1 Foundation -Boiler -West Side.

F3 Foundation -Boiler -West Side -Curing In Progress.

Installation Of Formwork -Bunker/Mill -B17 -B13 -BA-BB.

Inspection Of Steel Cages -Slag Conveyor -800mm dia. -SinoHydro.

PIT -Pile #T247 -1000mm dia. -Turbine Hall.

Preparation For MLT -Pile #T282 -1000mm dia. -Turbine Hall -SinoHydro.

BOP -MCWS -Backfilling In Progress.

Tower Crane Parts -To Be Installed & Utilized @ Turbine Hall.

BOP -Coal Yard -North Side -Preparation For MLT.

BOP -Chimney -Installation Of Steel Cage -Pile #HN41-1200mm dia. -EconPile.

Fabric Filter -Installation Of Steel Reinforcement -Pile Caps.

F1 Foundation -Boiler -West Side -Excavation In Progress.

21.12.2011

Consortium Office -Alstom -1st Floor.

Consortium Office -Alstom -Grd.Floor.

Fabric Filter -Hacking Of Piles.

Sheet Piling -Coffer Dam -F1 Foundation -Boiler -West Side.

Preparation For MLT -Pile #T282 -1000mm dia. -Turbine Hall.

Steel Reinforcement -Bunker/Mill -B13 -Type 3A -BA-BB.

Bunker/Mill -Installation Of Formwork -B17-B13 -BA.


BOP -Water Intake/Offshore -Preparation -Casting Yard -Box Culvert -Murray Robert.

BOP -Water Intake/Offshore -Preparation -Casting Yard -Box Culvert -Murray Robert.

BOP -Chimney -Preparation To Commence Boring -Pile #HN41-1200mm dia. -EconPile.

20.12.2011

PIT -Fabric Filter -25points.

Steel Reinforcement -Foundations -Fabric Filter.

Steel Fixing -Tie Beam -Bunker/Mill -B15 -B13 -BB.

Installation Of Formwork -Tie Beam -Bunker/Mill -B17 -B15 -BB.

Chipping & Cleaning -Surface Preparation -Construction Joint -Bunker/Mill -1st Phase Foundation.

Delivery Of Sheet Piles -Preparation For Coffer Dam -F3/F6 -Boiler -East Side.

Dismantling Of Formwork -F6 Foundation -Boiler -West Side.

Dismantling Of Formwork -F6 Foundation -Boiler -West Side.

Applying Of Curing Compound -F6 Foundation -Boiler -West Side.

PDA Test -Pile # A22 -800mm dia. -Fabric Filter.

19.12.2011

Fabric Filter -Lean Concrete -Tie Beams.

F2 Foundation -Boiler -East Side -Preparation For Pile Hacking / Lean Concrete.

Sheet Piles -Preparation For F1 Foundation -Boiler -West Side.

Steel Reinforcement -Fabric Filter -Foundations.

Steel Fixing -Tie Beam -Bunker/Mill -B17 -B13 -BA.

Steel Reinforcement -Tie Beam -Bunker/Mill -B17 -BA -BB.

Chipping For Construction Joint -Bunker/Mill -1st Phase Foundation -B3.

Inspection -Steel Reinforcement -Tie Beams -Bunker/Mill -B17 -B13 -BA / BB.

BOP -Chimney -Steel Cages Preparation For Bore Pile -1200mm dia.-EconPile.

Consortium Office -Alstom -Grd.Floor.

Consortium Office -Alstom -Grd. Floor.

Consortium Office -Alstom -Grd. Floor.

Consortium Office -Alstom -1st Floor.

Consortium Office -Alstom -1st Floor.