22.09.2011

Weekly Safety Tool Box Meeting -Alstom/Cmc/MudaJaya.

Fabrication Of Steel Cages -Bore Pile -Turbine Hall -Synohydro

Concreting To Base Slab -Consortium Office.

Concreting To Pile #T248 -1000mm dia. -Turbine Hall -Synohydro.

Preparation For Load Test -Pile # B93-800mm dia. -Boiler.

Finishing Works To Base Slab -Consortium Office.

21.09.2011

Preparation For Load Test (MLT) -Pile Point # B93-800mm dia. -Boiler.

Finishing Works To Base Slab-Consortium Office -CMC.

Final Preparation Prior Concreting To Base Slab -Consortium Office -Alstom.

Concreting To Ground Beam -Consortium Office.

Concreting (Build-Up) To MLT Pile Point # B82-1000mm dia. -Boiler.

Concreting To 1st Pile For Synohydro @ Turbine Hall -Pile # T241 -1000mm dia.

Turbine Hall -Bore Pile Working Area -Synohydro.

20.09.2011

Final Preparation Prior Commencement Of Boring Works -Turbine Hall -Synohydro.

Construction Of Silt Trap.

Final Preparation Prior Concreting To Base Slab -Consortium Office.

Concreting To Base Slab -Consortium Office.

20.09.2011

19.09.2011

Bore Rigs -BG25 -Hydraulic -To Be Utilized At Turbine Hall -Synohydro.

Preparation Of Bentonite Pipes -Turbine Hall -Synohydro.

Treme Pipes -Bore Pile Works -Turbine Hall -Synohydro.

Survey Setting Out -Pile Points -Turbine Hall -Synohydro.

Slab Preparation -Consortium Office.

Slab Preparation -Consortium Office.

18.09.2011

3No. Sinohydro Rigs with Jibs Raised,
Shafts, drive units and certification due this week.

17.09.2011

Balance of Sinohydro equipment arrives for installation on new piling rigs.

3No. Piling rig jibs complete for inspection prior lifting into position.

Sinohydro engineers commence setting out and finalising rig positions.

Sinohydro preparing laydown area

Econpile continue to progress boiler piling

MLT balast and beam deliveries & positioning complete