Weekly Safety Tool Box Meeting -Alstom/Cmc/MudaJaya.
21.09.2011
17.09.2011
Balance of Sinohydro equipment arrives for installation on new piling rigs.
3No. Piling rig jibs complete for inspection prior lifting into position.
Sinohydro engineers commence setting out and finalising rig positions.
Sinohydro preparing laydown area
Econpile continue to progress boiler piling
MLT balast and beam deliveries & positioning complete
Subscribe to:
Posts (Atom)