07.04.2012


 Flue Gas Duct-Pipe Duct-Excavation of Bored Piling in Progress

Chimney-Steel Fixing of Top Bars of the Base Foundation in Progress
 F11-Boiler-Final Preparation of Base Foundation Prior for Concreting
 F8-Boiler-Prepartion Prior for Steel Fixing of Base Foundation

 Boiler-East Side-Backfilling and Compaction in Progress
 Mill-South Side-Backfilling in Progress
 Mill A&B-Retaining Wall-Formworks Installation of Wall in Progress
Mill E-Mechanical-Scaffolding Erection in Progress
Turbine Hall-Tower Crane Preparation Prior for Erection
 Turbine Hall-Lean Concreting Completed
 Turbine Hall-East Side-Excavation for Box Tie in Progress
Central Electrical Building-Steel Fixing of Base Foundation in Progress
 Phase 1-Main Cooling Water (MCW)-Pedals for MCW Pipes
  Phase 1-Main Cooling Water (MCW)-Formworks Fabrication in Progress
  Phase 1-Main Cooling Water (MCW)- Spun Pile Cutting in Progress
 Phase 1-Sea Water Flue Gas Desulphurisation-Glass Reinforced Pipes-Backfilling and Compaction in Progress





06.04.2012

Chimney-Steel Fixing of Top Bars and Formworks Installation of Base Foundation in Progress
 F1-Boiler-Steel Fixing and Formworks Installation of Stumps in Progress
 F4-Boiler-Final Preparation of Base Foundation Prior for Concreting
 F9-Boiler-Casting Completed and Forworks Installation of Stumps in Progress
 F11-Boiler-Formworks Installation of Base Foundation in Progress
 F10-Boiler-Casting Completed and Removal of Formworks in Progress
Boiler Ash Pit- Formworks Installation 2nd Stage Perimeter Wall in Progress
 Mill H-  TNBJ Witnessing for the Setting up of the Packer Plate
 Mill B-Retaining Wall-Casting Completed and Curing in Progress
  Mill E-Retaining Wall-Casting Completed and Curing in Progress
 Mill A-Backfilling of South Side Area in Progress
Mill F-Mechanical-Scaffolding Erection in Progress

 Phase 1-Main Cooling Water-Excavation in Progress
Turbine Hall- Excavation of South Side Area in Progress


05.04.2012

Chimney-Steel Fixing Bottom Bars and Forworks Installation of Base Foundation in Progress
 F4-Boiler-Final Preparation of Base Foundation Prior for Concreting in Progress
 F1-Boiler-Casting Completed in Stumps and Removal of Formworks in Progress
 F9-Boiler-Final Preparation of Base Foundation Prior for Concreting in Progress
 F11-Boiler-Formworks Installation of Base Foundation in Progress
 F10-Boiler-Final Preparation of Stumps Prior for Concreting in Progress

F5-Boiler-Final Preparation of Base Foundation Prior for Lean Concreting in Progress 
 Mill G-Mechanical-Scaffolding Erection in Progress
Mill H-Mechanical-Preparation of Base Foundation for Pulverizer in Progress
 Turbine Hall-Base Raft Foundation Curing in Progress
  Turbine Hall-Base Raft Foundation Cover with Polystyrene for Insulataion
Turbine Hall-South Side Excavation in Progress
 Central Electrical Building- Steel Fixing of Base Foundation in Progress
  Central Electrical Building- Steel Fixing of Base Foundation in Progress
Phase 1-Main Cooling Water-Lean Concrete Casting Completed
 Phase 1- Fuel Gas Desulfurization Glass Reinforced Pipes-Backfilling in Progress
Boiler-Material Delivery-Main Column in Progress
Fuel Gas Duct-Duct Pipes-Hoisting of Bored Pile Steel Reinforcement in Progress

04.04.2012


APS, CMC and Mudajaya-Keep on Track for the Completion of Casting in the Turbine Hall Base Raft Foundation
 Turbine Hall-Casting Completed, Trowelling and Curing in Progress 
  Turbine Hall-Casting Completed, Trowelling and Curing in Progress 
 Turbine Hall-Casting Completed, Trowelling and Curing in Progress  
Turbine Hall-Hoisting of Polystyrene for the Surface Protection of Base Raft Foundation
 Chimney-Steel Fixing of Bottom Bars and Formworks Installation in Progress
 F10-Boiler-Final Preparation Prior for Concreting
 F11-Boiler-Formworks Installation Base Foundation in Progress 
  F9-Boiler-Final Preparation Prior for Concreting
  F4-Boiler-Final Preparation Prior for Concreting 
F4-Boiler-Steel Fixing of Stumps in Progress
 F1-Boiler-Final Preparation Prior for Concreting
 Mill E-Retaining Wall Formworks Installation in Progress
Mill C-Retaining Wall Formworks Installation in Progress
 Phase 1-Main Cooling Water-Preparation Prior for Lean Concreting
 Phase 1-Fuel Gas Desulfurization Glass Reinforced Pipes-Formation Level of Backfilling and Dewatering in Progress
 Turbine Hall-South Side-Box Tie in Progress
 Turbine Hall-South Side-Box Tie in Progress
Boiler-Mechanical-Boiler Main Steel Column Stock at East Side of the Boiler