27.01.2012

Bar Bending Yard -Fabric Filter.

Fabric Filter -Formwork Installation -Pile Caps & Tie Beams -Gridline -6.

F4 Foundation -Type E -Boiler -Steel Fixing -Bottom Layer.

F3 -Boiler -East Side -Curing In Progress.

F2 Foundation -Type F -Boiler -East Side -Steel Fixing Top Layer In Progress.

Mill -C -Steel Fixing -2nd Stage Pour In Progress.

Turbine Hall -2nd Stage Excavation (-2.1MLSD) In Progress.

Turbine Hall -Excavation -2nd Stage (-2.1MLSD).

CEB -Preparation For Lean Concrete (Pile Caps & Tie Beams).

CEB -Preparation For Lean Concreting.(Pile Caps & Tie Beams)

25.01.2012

F2 -Type A/B/C -Boiler -East Side -Curing In Progress.

Weekly EHS -Management Walkdown.

Brickwall Formwork -Mill -D.

Mill -C -Preparation For Steel Fixing -2nd Stage.

Steel Reinforcement Fabrication Yard -Mills.

Steel Reinforcement Fabrication Yard -Mills.

Boring To Pile #A03-800mm dia. -Absorbers Foundation -SinoHydro.

Concreting To Pile #A91-800mm dia. -Absorbers Foundation -SinoHydro.

F2-Type F -Boiler -East Side -Steel Fixing -Bottom Layer In Progress.

Mill -C -Steel Fixing -2nd Stage In Progress.