Condensate Pump Pit-Curing Of Concrete
Fabric Filter-Compaction at East Side in ProgressF2-Boiler-Formworks Removal in Progress
F5-Boiler- Steel Fixing and Formworks Installation in Progress
F4-Boiler- Steel Fixing and Formworks Installation in Progress
F2-Boiler- Final Preparation Prior to Concreting
F1-Boiler- Backfilling and Compaction in Progress
F9-Boiler- Steel Fixing and Formworks Installation in Progress
Boiler Ash Pit-Final Preparation Prior to Concreting
F8-Boiler- Preparation for Lean Concreting
Mill A-Final Preparation Prior for Concreting
Mill A-Final Preparation Prior for Concreting
Turbine Hall- Steel Fixing and Formwork Installation in Progress
Turbine Hall- Steel Fixing and Formwork Installation in Progress
Central Electrical Building-Final Preparation Prior for Lean Concreting
Phase 3-Main Cooling Water-Spun Piles Delivery
Phase 1-Main Cooling Water- Excavation in Progress
Phase 1 Flue Gas Desulfurization-GRP-Backfilling in Progress
Mill-Retaining Wall South Side-Concrete Curing of Base Foundation
Mill-Retaining Wall South Side-Wall Formworks Installation in Progress
Mill South Side-Backfilling in Progress
F11-Boiler-Concrete Curing of Stumps
Fuel Gas Duct- Preparation of Bored Pile Prior for Concreting
Eversendai-Site Office Construction in Progress
Boiler-Material Delivery 1st Batch of Boiler Duct
Boiler-Material Delivery 1st Batch of Boiler Duct