29.03.2012

 Chimney-Steel Fixing-Bottom Layer Base Foundation in Progress

 Condensate Pump Pit-Curing Of Concrete
 Fabric Filter-Compaction at East Side in Progress
 F2-Boiler-Formworks Removal in Progress
 F5-Boiler- Steel Fixing and Formworks Installation in Progress
 F4-Boiler- Steel Fixing and Formworks Installation in Progress 
 F2-Boiler- Final Preparation Prior to Concreting


 F1-Boiler- Backfilling and Compaction in Progress
  F9-Boiler- Steel Fixing and Formworks Installation in Progress 
 Boiler Ash Pit-Final Preparation Prior to Concreting
  
 F8-Boiler- Preparation for Lean Concreting
 Mill A-Final Preparation Prior for Concreting
  Mill A-Final Preparation Prior for Concreting
 Turbine Hall- Steel Fixing and Formwork Installation in Progress
  Turbine Hall- Steel Fixing and Formwork Installation in Progress
 Central Electrical Building-Final Preparation Prior for Lean Concreting
 Phase 3-Main Cooling Water-Spun Piles Delivery
 Phase 1-Main Cooling Water- Excavation in Progress
Phase 1 Flue Gas Desulfurization-GRP-Backfilling in Progress  
 Mill-Retaining Wall South Side-Concrete Curing of Base Foundation
 Mill-Retaining Wall South Side-Wall Formworks Installation in Progress
 Mill South Side-Backfilling in Progress
 F11-Boiler-Concrete Curing of Stumps
 Fuel Gas Duct- Preparation of Bored Pile Prior for Concreting
Eversendai-Site Office Construction in Progress 
Boiler-Material Delivery 1st Batch of Boiler Duct 
Boiler-Material Delivery 1st Batch of Boiler Duct