Steel Cage Installation -Pile #HN36-1200mm dia. -Chimney -BOP -SinoHydro.
Boring To Pile #HN08-1200mm dia. -Chimney -BOP -EconPile.
F1 -Foundation -Boiler -West Side -Steel Fixing -Stump.
Crushing Of Hacked Piles -Boiler.
F4-Foundation-Type A -Boiler -East Side -Preparation For Steel Fixing.
F10-B14 -Foundation -Boiler -East Side -Steel Fixing -Bottom Layer In Progress.
F11-B4 -Foundation -Boiler -West Side -Excavation In Progress.
F6 -Boiler -West Side -Cleaning Prior Formwork Installation.
F6 -Foundation -Boiler -West Side -Hacking Works (Construction Joint -Stump).
F6 Foundation -Type -A -Boiler -West Side -Formwork Installation.
F10 -B14 -Boiler -East Side -Steel Fixing -Bottom Layer In Progress.
Mill-H -Installation Of Formwork.
Mill-H -Installation Of Formwork.
Turbine Hall -Excavation-3rd Stage Down To Level (-3.6MLSD).
Turbine Hall -Excavation 3rd Stage In Progress (-3.6MLSD).
CEB -Hacking Of Piles In Progress -Gridline -2 -A/G.
CEB -Preparation For Lean Concrete -Grid 1 -A-G.
F4-Type-E -Boiler -East Side -Curing In Progress.