Chimney-Steel Fixing Bottom Bar Base Foundation in Progress
Fues Gas Duct-Excavation of Bored Piling in Progress
Fues Gas Duct-Steel Fixing of Bored Piling in Progress
F5-Boiler-Casting completed of Base Foundation and Curing in Progress
F1-Boiler-Formworks Installation of Stumps in Progress
F4-Boiler-Formworks Installation of Base Foundation in Progress
Boiler Ash Pit-Backfilling and Steel Fixing in Progress
F1-Boiler-Casting Completed of Base Foundation of GL B16.6-BC to GL B16.3-BD.5 and Formworks Installation in Progress of GL B16.3-BC to GL B16.3-BD.5
F11-Boiler-Steel Fixing of Base Foundation in Progress
F1-Boiler-Formworks Installation of Stumps in Progress
Mill A-Formworks Removal in Progress
Central Electrical Building- Preparation Prior for Lean Concreting
Central Electrical Building- Steel Fixing of Base Foundation in Progress
Central Electrical Building-Hacking of Bored Piles in Progress
Phase 1-Main Cooling Water-Excavation in Progress
Phase 1-Fuel Gas Desulfurization-Glass Reinforced Pipes-Backfilling in Progess
Turbine Hall-Final Preparation Prior for Concreting
Turbine Hall-Final Preparation Prior for Concreting
Turbine Hall-Final Preparation Prior for Concreting
Mill H-Eversendai-Scabbling of Pulverizer Foundation in Progress
Mill F-Retaining Wall South Side Casting Completed and Curing in Progress
Mill D-Retaining Wall South Side Casting Completed and Removal of Formworks in Progess
Boiler-Material Delivery -Secondary Steel Column