12.11.2011

Consortium Office -Alstom -Brick Laying /Installation Of Trusses/Purlins/Frames In Progress.

Consortium Office -Alstom -Preparation Of Mock-Up Unit -Grd. Floor.

Consortium Office -Alstom -Preparation Of Mock-Up Unit -Grd. Floor.

Consortium Office -Alstom -Preparation Of Mock-Up Unit -Grd. Floor.


Boring To Pile #B07-800mm dia. -FGD Building. -EconPile.

Boring To Pile #B13 -800mm dia. -FGD Building. -EconPile.

Bore Rig -HR240 -Hydraulic -Dismantling For Demobilization -EconPile.


MLT -Pile # B57 -1200mm dia. -Boiler -To Commence On 14.11.2011 -1141Ton. -EconPile.

Concreting To Pile #T249 -1000mm dia. -Turbine Hall -SynoHydro.

MCB -Area -Preparation To Commence With Bore Pile Works -800mm dia. -96Points -SynoHydro.

BOP -MCWS -Backfilling In Progress.

11.11.2011

Laying Of Bricks -Consortium Office -Alstom -Grd.Floor -Wash Rooms.

Brickworks -Consortium Office -Alstom -Wash Rooms.

Hacking Of Piles -Bunker/Mill -B9.

Preparation For Lean Concrete -Pile Cap -Bunker Mill -B15.

Consortium Office -Alstom -Preparation For Mock-Up Unit In Progress.

Sheet Piling -Boiler Area -Preparation For Coffer Dam -Type F3/F6 Foundation.

Sheet Piling -Preparation For Coffer Dam -Boiler Area -Foundation Type F3/F6.

Hacking Of Piles -Bunker/Mill -B9.

Lean Concreting In Progress -Pile Cap -Bunker/Mill -B13.

Lean Concreting In Progress -Pile Cap -Bunker/Mill -B15.

09.11.2011


Installation of secondary Steelwork to Block 1 (Alstom) of EPC office.

Curing of 1st Phase pour Mill C & Steel fixing on Mill D.

1st Phase, Mill A ready to pour. ( 48m3)

Curing and concrete finishing to 1st phase pour Mill B.


Blinding on Mill E


Econ Pile - Boiler Electrical Building (B35)

Econpile - Piling on FGD Electrical Building (B37)

10.11.2011

Consortium Office.

Bunker/Mill -Lean Concrete -Pile Cap -B9.

Excavation -Boiler Area -Type F3 Foundation -EL-5-000.

Concreting To Bunker/Mill -Pile Cap -Foundation -B7.

04.11.2011

Safety Tool Box Meeting -Econpile.

Concreting To Bunker/Mill -Pile Cap Foundation -1st Pour -B1.

Steel Fixing -Bunker/Mill -Pile Cap -B7 -1st Pour.

03.11.2011

Bunker/Mill -Pile Cap -Foundation -1st Pour -B1 -Installation Of Formwork.

Consortium Office -Laying Of Bricks / Installation Of Roof Trusses/Purlins -In Progress.

MCWS -BOP -Backfilling In Progress.

Steel Fixing -Bunker/Mill -Pile Cap Foundation -B1.

Steel Fixing -Bunker/Mill -Pile Cap -B5.

02.11.2011

Steel Fixing -Bunker/Mill -Pile Cap Foundation -B5

Pile Cap -Bunker Mill -B7 -Lean Concrete Completed.

01.11.2011

Steel Fixing -Bunker/Mill -Pile Cap -B5.

MCWS -BOP -Backfilling In Progress.

Consortium Office -Laying Of Bricks/Roof Trusses/Purlins -In Progress.