27.03.2012

Phase 2-Flue Gas Desulphurisation-Sheet Piling
 Chimney-Steel Fixing-Bottom Layer Base Foundation in Progress
F2-Boiler-Ground Beam Ready for Concreting
 F2-Boiler-Formworks Layout Inspection in Progress
 Mill B-Curing of Concrete
 Mill A- Formworks Installation in Progress
 Mill A-Steel Fixing in Progress
 Phase 1-Main Cooling Water (MCW)-Under New HV Line-Excavation in Progress
 Central Electrical Building (CEB)- Pile Cutting and Lean Concrete Preparation in Progress
 Turbine Hall-Formworks and Steel Fixing in Progress
 Condensate Pump Pit-Formworks Installation in Progress
 Turbine Hall-Steel Fixing Top Layer Raft Foundation in Progress
  Turbine Hall-Steel Fixing to Stumps Raft Foundation in Progress
 Mill G-Retaining Wall-Formworks Installation in Progress
 F11-Boiler-Formworks Installation in Progress
 F9-Boiler-Steel Fixing Installation in Progress

 Boiler Ash Pit-Formworks Installation in Progress
 F4-Boiler-Formworks Installation and Steel Fixing in Progress