MJG4
21.10.2011
Bunker/Mill -Area- Cutting Of Piles.
Hacking Of Piles -A14-800mm dia. -Bunker/Mill.
Consortium Office -Installation Of Purlins/Beams.
Consortium Office -1st Floor -Laying Of BRC In Progress.
20.10.2011
Weekly Safety Tool Box Meeting -Alstom/CMC/MudaJaya/GIGA/Synohydro/Econpile.
Installation Of Dewatering Pipes -Boiler -North Perimeter.
Hacking Of Pile -Bunker/Mill -B3 -Pile # A16-800mm dia.
Installation Of BRC -1st Floor Slab -Consortium Office.
19.10.2011
1st Floor Slab -Consortium Office.
Hacking Of Piles -Bunker -B1 -Pile #A75 & A07 -800mm dia.
Sheet Piling -Turbine Hall -South Perimeter.
Excavation To Boiler Area -East Side.
18.10.2011
Consortium Office.
Preparation For MLT -Pile #B82-1000mm dia. -Boiler.
Concreting To 1st Floor Slab -Consortium Office.
Installation Of Dewatering Pipes -Boiler -North Perimeter.
17.10.2011
Lean Concrete -Pile Cap -Bunker/Mill.
Installation Of Steel Cages -Pile #T081-Turbine Hall.
Preparation For MLT -Pile #B82-1000mm dia. -Boiler.
Installation Of Side Formwork -1st Floor Slab -Consortium Office.
Laying Of BRC -1st Floor Slab -Consortium Office.