21.10.2011

Bunker/Mill -Area- Cutting Of Piles.

Hacking Of Piles -A14-800mm dia. -Bunker/Mill.

Consortium Office -Installation Of Purlins/Beams.

Consortium Office -1st Floor -Laying Of BRC In Progress.

20.10.2011

Weekly Safety Tool Box Meeting -Alstom/CMC/MudaJaya/GIGA/Synohydro/Econpile.

Installation Of Dewatering Pipes -Boiler -North Perimeter.

Hacking Of Pile -Bunker/Mill -B3 -Pile # A16-800mm dia.

Installation Of BRC -1st Floor Slab -Consortium Office.

19.10.2011

1st Floor Slab -Consortium Office.

Hacking Of Piles -Bunker -B1 -Pile #A75 & A07 -800mm dia.

Sheet Piling -Turbine Hall -South Perimeter.




Excavation To Boiler Area -East Side.

18.10.2011

Consortium Office.

Preparation For MLT -Pile #B82-1000mm dia. -Boiler.

Concreting To 1st Floor Slab -Consortium Office.

Installation Of Dewatering Pipes -Boiler -North Perimeter.

17.10.2011

Lean Concrete -Pile Cap -Bunker/Mill.

Installation Of Steel Cages -Pile #T081-Turbine Hall.

Preparation For MLT -Pile #B82-1000mm dia. -Boiler.

Installation Of Side Formwork -1st Floor Slab -Consortium Office.

Laying Of BRC -1st Floor Slab -Consortium Office.