14.10.2011

Consortium Site Office.

Preparation For Lean Concreting -Pile Cap -Bunker/Mill -B5.

Lean Concreting To Pile Cap -Bunker/Mill -B7.


Concreting To Pile #T010-1000mm dia. -Turbine Hall.

13.10.2011

Installation Of Dewatering Pipes -Boiler -West Perimeter.

Perimeter Drain / Preparation For Appron Slab -Consortium Office.

Pre-Cast Slabs -1st Floor -Consortium Office.

12.10.2011

Sheet Piling To Turbine Area -North Perimeter.

EHS-SAPI -Briefing/Presentation -ALSTOM-Attended By CMC/MCB/ECONPILE/SYNOHYDRO/GIGA/TEPSCO/TNBJ.

Concreting To Pile #A04-800mm dia. -Boiler/Filter Fan.

Installation Of De-Watering Pipes -Boiler -West Perimeter.

11.10.2011

Installation Of Steel Cages -Pile#T060 -1000mm dia. -Turbine Hall.

Installation Of Perimeter Drain -Consortium Office.

MCWS -Backfilling In Progress.

Sheet Pile -Turbine Area -North Perimeter.

10.10.2011

Concreting To Pile#196-1000mm dia. -Turbine Hall.

Pre-cast Slabs -1st Floor -Consortium Office.

Sheet Pile To Bunker Area -Grid Line B7 -Grid Line B1.

MCWS -Backfilling In Progress.