16.09.2011
Sino Hydro start jib assembly of 4 N0. new BG 25 rigs.
Bauer Customer support on site to assist.
All kentelage deliveries complete and placed for first MLT testing
Econpile continue to progress Boiler, now 64% complete.
Turbine Hall Excavation to Pile mat level complete.
Sino Hydro due to start piling 18/09
15.09.2011
Safety Tool Box Meeting -CMC/ALSTOM.
Bore Pile Area -Boiler & Ash Hopper.
Steel Cage Fabrication -Bore Pile Turbine Hall -Synohydro.
Bore Rigs -4nos. -Synohydro -To Be Utilized For Turbine Hall Bore Pile Works.
Concreting To Ground Beams -Consortium Office.
14.09.2011
Installation Of Steel Reinforcement -Ground Beams -Consortium Office.
MCWS -Backfilling Works -Piping Systems Area.
Concreting To Ground Beams -Consortium Office.
Concreting To Ground Beams -Consortium Office.
Removing Of Casing -Pile # D13-1000mm dia. -Ash Hopper.
14/09/2011
20 Artic's of MLT testing & SynoHydro piling equipment arrives over night.
Syno Hydro Bauer Piling Rigging start arrive on site.
Early morning toolbox talk with general Civil workers and Management.
13.09.2011
Preparation Of Ground Beams -Consortium Office.
Installation Of Plug -Pile # D15 -1000mm dia. -Ash Hopper
Bore Pile -Area -Boiler /Ash Hopper.
Backfilling -MCWS -Area -Pipes System.
12.09.2011
Installation Of Pipes -Water Supply/Sewerage System -Consortium Office.
Steel Reinforcement -Ground Beams -Consortium Office.
Soil Investigation -BOP -Screening Hall.
Boring To Pile # B98 -1000mm dia. -Boiler.
Bore Pile Area -Boiler.
MCWS -Backfilling Works In Progress -BOP -Pipes System.
Concreting To Pile # B62-1200mm dia. -Boiler.
11.09.2011
Bar Bending -Steel Reinforcement Preparation -Ground Beams -Consortium Office.
Steel Reinforcement -Ground Beams -Consortium Office.
Steel Reinforcement -Ground Beams -Consortium Office.
Concreting To Pile # B85 -1000mm dia. -Boiler.
Bore Pile Area -Boiler.
10.09.2011
Safety Tool Box Meeting -CMC/MudaJaya/Econpile.
Steel Reinforcement -Ground Beams -Consortium Office.
Excavation For Pipes -Water Supply And Sewerage System -Consortium Office.
Steel Reinforcement -Ground Beams -Consortium Office.
Bore Pile Area -Boiler.
Steel Cages Preparation -Bore Pile -Turbine Hall -Synohydro.