16.09.2011


Sino Hydro start jib assembly of 4 N0. new BG 25 rigs.
Bauer Customer support on site to assist.


All kentelage deliveries complete and placed for first MLT testing


Econpile continue to progress Boiler, now 64% complete.


Turbine Hall Excavation to Pile mat level complete.
Sino Hydro due to start piling 18/09

15.09.2011

Safety Tool Box Meeting -CMC/ALSTOM.

Bore Pile Area -Boiler & Ash Hopper.

Steel Cage Fabrication -Bore Pile Turbine Hall -Synohydro.

Bore Rigs -4nos. -Synohydro -To Be Utilized For Turbine Hall Bore Pile Works.

Concreting To Ground Beams -Consortium Office.

14.09.2011

Installation Of Steel Reinforcement -Ground Beams -Consortium Office.

MCWS -Backfilling Works -Piping Systems Area.


Concreting To Ground Beams -Consortium Office.

Concreting To Ground Beams -Consortium Office.

Removing Of Casing -Pile # D13-1000mm dia. -Ash Hopper.

14/09/2011


20 Artic's of MLT testing & SynoHydro piling equipment arrives over night.

Syno Hydro Bauer Piling Rigging start arrive on site.

Early morning toolbox talk with general Civil workers and Management.

13.09.2011

Preparation Of Ground Beams -Consortium Office.

Installation Of Plug -Pile # D15 -1000mm dia. -Ash Hopper

Bore Pile -Area -Boiler /Ash Hopper.

Backfilling -MCWS -Area -Pipes System.

12.09.2011

Installation Of Pipes -Water Supply/Sewerage System -Consortium Office.

Steel Reinforcement -Ground Beams -Consortium Office.

Soil Investigation -BOP -Screening Hall.

Boring To Pile # B98 -1000mm dia. -Boiler.

Bore Pile Area -Boiler.

MCWS -Backfilling Works In Progress -BOP -Pipes System.

Concreting To Pile # B62-1200mm dia. -Boiler.

11.09.2011

Bar Bending -Steel Reinforcement Preparation -Ground Beams -Consortium Office.

Steel Reinforcement -Ground Beams -Consortium Office.

Steel Reinforcement -Ground Beams -Consortium Office.


Concreting To Pile # B85 -1000mm dia. -Boiler.

Bore Pile Area -Boiler.

10.09.2011

Safety Tool Box Meeting -CMC/MudaJaya/Econpile.

Steel Reinforcement -Ground Beams -Consortium Office.

Excavation For Pipes -Water Supply And Sewerage System -Consortium Office.

Steel Reinforcement -Ground Beams -Consortium Office.

Bore Pile Area -Boiler.

Steel Cages Preparation -Bore Pile -Turbine Hall -Synohydro.