31.03.2012

 Chimney-Steel Fixing Bottom Layer Base Foundation in Progress
 Mill A Removal of Formworks in Progress
 Central Electrical Building-Steel Fixing Base Foundation in Progress
 Turbine Hall-Hacking of Bored Piles East Side in Progress
 Phase 1-Flue Gas Desulfurization Glass Reinforced Pipes-Backfilling in Progress 
 Mill F-Retaining Wall-South Side Formworks in Progress 
 Mill D-Retaining Wall-South Side Formworks in Progress 
 Turbine Hall-Final Preparation Prior to Concreting and Cleaning of Debris
 Turbine Hall-West Side Setting up of Spot Lights 
 F10-Boiler-Hacking of Bored Piles and Removal of Debris
 Mill H-Eversendai-Scaffolding Installation in Progress
Flue Gas Duct-Bored Piles Rebar Installation in Progress 
 Mill H and Mill G-Eversendai-Steel Plates for Crane Base Pads

 F4-Boiler-Base Foundation Steel Fixing and Formworks Installation in Progress
 F5-Final Preparation Prior to Concreting
  F1-Boiler-Stumps Formworks Installation in Progress

 F9-Boiler-Base Foundation Steel Fixing and Formworks Installation in Progress
 F10-Boiler-Stumps Formworks Installation in Progress

30.03.2012

 F2-Boiler-Base Foundation Casting Completed and Curing in Progress
 F11-Boiler-Steel Fixing- Base Foundation in Progress
 F4-Boiler-Formworks Installation and Steel Fixing of Base Foundation in Progress
  F5-Boiler-Final Preparation Prior Concreting
  F1-Boiler-Formworks Installation of Stumps in Progress
   F6-Boiler-Stumps Casting Completed and Curing in Progress
 F10-Boiler- Steel Fixing of Stumps in Progress
 F10-Boiler- Hacking of Bored Piles in Progress
 Boiler Ash Pit-2nd Stage Casting Completed and Curing in Progress
F9-Boiler-Steel Fixing and Formworks Installation in Progress
Boiler-Material Delivery-Ductwork 
Central Electrical Building-Preparation Prior Lean Concreting
Central Electrical Building-Preparation For Steel Fixing-Pile Cap
Chimney-Steel Fixing Bottom Layer Base Foundation in Progress
Condensate Pump Pit- 2nd Stage Casting Completed-3 nos.
Mill G and H- Platform and Access Preparation for Boiler Group


Boiler Group-Laydown Area Temporary Fence Installation in Progress
Boiler Electrical Building-Excavation in Progress
Flue Gas Duct- Bored Piling in Progress
Glass Reinforced Pipes-Pipes-Laydown Area
Phase 1-Flue Gas Desulfurization-Glass Reinforced Plastic-Backfilling in Progress 
Phase1-Main Cooling Water-Excavation in Progress
Mill-Retaining Wall South Side Steel Fixing and Formworks Installation in Progess
Mill A-Casting Completed and Curing in Progress 
Mill H-Eversendai-Scaffolding Installation In Progress
Chimney-Steel Fabrication in Progress
Survey Inspection-Turbine Hall-Column Alignment
Turbine Hall-Steel Fixing and Formworks Installation in Progress
Turbine Hall-Steel Fixing and Formworks Installation in Progress
Turbine Hall-Steel Fixing and Formworks Installation in Progress
Turbine Hall-Hacking Bored Piles in Progress
Turbine Hall-Cofferdam Box Tie in South side