29.09.2011

Steel Structures For Columns -Consortium Office.

Concreting To Pile #T238-1000mm dia. -Turbine Hall -Synohydro.

Erection Of Steel Structures For Columns -Consortium Office.

MCWS -Backfilling In Progress.

Installation Of Geotextile & Laying Of Rocks -Silt Trap.

28.09.2011

Excavation To Bunker Area.

Bore Pile Working Area -Turbine Hall.

Erection Of Steel Structures For Columns -Consortium Office.



Erection Of Steel Structures For Columns -Consortium Office.

27.09.2011

Pile # T259 -1000mm dia. -Installation Of Steel Cage -Turbine Hall.

Bore Pile Working Area -Boiler

Sheet Piling To Turbine Hall -West Grid Line.

Excavation To Bunker Area -Preparation For Dewatering And Cutting Of Piles.

26.09.2011

Installation Of Treme Pipes -Pile #T252-1000mm dia. -Turbine Hall.

Concreting To Pile #T252-1000mm dia. -Turbine Hall.

MCWS -Backfilling In Progress.

MCWS -Backfilling In Progress.

25.09.2011

Preparation For MLT -Pile #B93-800mm dia. -Boiler.

Concreting To Base Slab -(Final Pour) -Consortium Office.

Concreting To Base Slab (Final Pour)-Consortium Office.

Concreting To Pile #T237-1000mm dia. -Turbine Hall.

24.09.2011

Weekly Safety Tool Box Meeting -Econpile.

Sheet Piling To Bunker /Turbine Area -North Side.

Survey Setting Out Prior Commencement Of Sheet Piling Works -Turbine/Bunker Area.


Concreting To Pile #T250-1000mm ida. -Turbine Hall.

23.09.2011

Bore Pile Working Area -Boiler.

MCWS -Backfilling In Progress.

Concreting To Pile #T255 -1000mm dia. -Turbine Hall.

Base Slab Preparation -Consortium Office -Last Portion.