29.09.2011
Steel Structures For Columns -Consortium Office.
Concreting To Pile #T238-1000mm dia. -Turbine Hall -Synohydro.
Erection Of Steel Structures For Columns -Consortium Office.
MCWS -Backfilling In Progress.
Installation Of Geotextile & Laying Of Rocks -Silt Trap.
28.09.2011
Excavation To Bunker Area.
Bore Pile Working Area -Turbine Hall.
Erection Of Steel Structures For Columns -Consortium Office.
Erection Of Steel Structures For Columns -Consortium Office.
27.09.2011
Pile # T259 -1000mm dia. -Installation Of Steel Cage -Turbine Hall.
Bore Pile Working Area -Boiler
Sheet Piling To Turbine Hall -West Grid Line.
Excavation To Bunker Area -Preparation For Dewatering And Cutting Of Piles.
26.09.2011
Installation Of Treme Pipes -Pile #T252-1000mm dia. -Turbine Hall.
Concreting To Pile #T252-1000mm dia. -Turbine Hall.
MCWS -Backfilling In Progress.
MCWS -Backfilling In Progress.
25.09.2011
Preparation For MLT -Pile #B93-800mm dia. -Boiler.
Concreting To Base Slab -(Final Pour) -Consortium Office.
Concreting To Base Slab (Final Pour)-Consortium Office.
Concreting To Pile #T237-1000mm dia. -Turbine Hall.
24.09.2011
Weekly Safety Tool Box Meeting -Econpile.
Sheet Piling To Bunker /Turbine Area -North Side.
Survey Setting Out Prior Commencement Of Sheet Piling Works -Turbine/Bunker Area.
Concreting To Pile #T250-1000mm ida. -Turbine Hall.
23.09.2011
Bore Pile Working Area -Boiler.
MCWS -Backfilling In Progress.
Concreting To Pile #T255 -1000mm dia. -Turbine Hall.
Base Slab Preparation -Consortium Office -Last Portion.