28.03.2012


 Flue Gas Duct-Bored Pile-Excavation in Progress 
 Eversendai-Site Office Construction in Progress
 Chimney-Steel Fixing-Bottom Layer Base Foundation in Progress
Fabric Filter-Backfilling and Compaction in Progress 
 Flue Gas Duct-Bored Pile-Preparation for Excavation in Progress 
 F5-Boiler-Formworks Installation in Progress
 F1-Boiler-Backfilling and Compaction in Progress
F4-Boiler-Formworks Installation and Backfilling and Compaction in Progress
F4-Boiler-Formworks Installation  in Progress
Boiler Ash Pit-Formworks Installation in Progress
F9-Boiler-Steel Fixing in Progress
F11-Boiler-Final Preparation Prior to Concreting
 Mill B- Formworks Removal in Progress
Condensate Pump Pit-Formworks Installation in Progress
F6-Boiler-Final Preparation Prior to Concreting
Mill A-Steel Fixing and Formworks Installation in Progress
Mill A-Steel Fixing and Formworks Installation in Progress
Turbine Hall-Steel Fixing and Formworks Installation for Raft Foundation in Progress
Turbine Hall- Hacking of Piles in Progress South Side
Central Electrical Building-Preparation for Lean Concrete
Phase 1-Flue Gas Desulfurization-Backfilling in Progress
Phase 4-Main Cooling Water-Sheet Piling in Progress
Phase 1-Main Cooling Water (MCW)-Excavation in Progress


Mill G & H-Retaining Wall-Steel Fixing and Formworks Installation in Progress
F11-Boiler-Removal of Debris and Preparation for Lean Concreting