Boring To Pile #A43 -800mm dia. -Absorbers Foundation -EconPile.
12.01.2012
Boring To Pile #A40-800mm dia. -Absorbers Foundation -EconPile.
Fabric Filter -Hacking Of Piles -Grid -7 To Grid-8.
Mill -G -Steel Reinforcement -2nd Stage Pour In Progress.
Turbine Hall -Excavation 2nd Stage In Progress -Down To Level -2.1MLSD (CWP Pipes Line).
Turbine Hall -2nd Stage Excavation -Down To Level -2.1MLSD In Progress. (CWP -Pipe Lines).
Bunker/Mill -B5 -BA/BB -Steel Fixing In Progress.
J-Bolt Frame -Mill -H -Preparation In Progress.
11.01.2012
Boring To Pile #A42-800mm dia. -Absorbers Foundation -EconPile.
Fabric Filter -Grid -7 -Grid 8 -Excavation In Progress.
F3 -Boiler -East Side -Steel Fixing -Bottom Layer.
F7 -Boiler -East Side -Installation Of Formwork In Progress.
Bunker/Mill -G -Brickwall Formwork In Progress.
10.01.2012
Concreting To Pile #A65-1000mm dia. -Absorbers Foundation -SinoHydro.
Sheet Piling -Coffer Dam -F5 -Type E -Foundation -Boiler.
F3 -Preparation To Commence With Steel Fixing -Bottom Layer.
F7 -Boiler -East Side -Steel Fixing In Progress -Scheduled For Castin On 14.01.2012.
Bunker/Mill -North Side -B17-B13 -BB -Backfilling & Compaction In Progress.
Bunker/Mill -B17 -North Side -Backfilling In Progress.
Mill -H -Preparation For Re-Bar/J-Bolts & Concreting -2nd Phase.
PIT -F3 -Boiler -East Side.
BOP -Sub-Station -Project Power Supply -Concreting To Base Slab.