30.03.2012

 F2-Boiler-Base Foundation Casting Completed and Curing in Progress
 F11-Boiler-Steel Fixing- Base Foundation in Progress
 F4-Boiler-Formworks Installation and Steel Fixing of Base Foundation in Progress
  F5-Boiler-Final Preparation Prior Concreting
  F1-Boiler-Formworks Installation of Stumps in Progress
   F6-Boiler-Stumps Casting Completed and Curing in Progress
 F10-Boiler- Steel Fixing of Stumps in Progress
 F10-Boiler- Hacking of Bored Piles in Progress
 Boiler Ash Pit-2nd Stage Casting Completed and Curing in Progress
F9-Boiler-Steel Fixing and Formworks Installation in Progress
Boiler-Material Delivery-Ductwork 
Central Electrical Building-Preparation Prior Lean Concreting
Central Electrical Building-Preparation For Steel Fixing-Pile Cap
Chimney-Steel Fixing Bottom Layer Base Foundation in Progress
Condensate Pump Pit- 2nd Stage Casting Completed-3 nos.
Mill G and H- Platform and Access Preparation for Boiler Group


Boiler Group-Laydown Area Temporary Fence Installation in Progress
Boiler Electrical Building-Excavation in Progress
Flue Gas Duct- Bored Piling in Progress
Glass Reinforced Pipes-Pipes-Laydown Area
Phase 1-Flue Gas Desulfurization-Glass Reinforced Plastic-Backfilling in Progress 
Phase1-Main Cooling Water-Excavation in Progress
Mill-Retaining Wall South Side Steel Fixing and Formworks Installation in Progess
Mill A-Casting Completed and Curing in Progress 
Mill H-Eversendai-Scaffolding Installation In Progress
Chimney-Steel Fabrication in Progress
Survey Inspection-Turbine Hall-Column Alignment
Turbine Hall-Steel Fixing and Formworks Installation in Progress
Turbine Hall-Steel Fixing and Formworks Installation in Progress
Turbine Hall-Steel Fixing and Formworks Installation in Progress
Turbine Hall-Hacking Bored Piles in Progress
Turbine Hall-Cofferdam Box Tie in South side