14.04.2012

Excavation work around stack 
Stack foundation rebar 
Bored piling between FF and Boiler 
Boiler east side (facing south )
Boiler F4 
Boiler F9 
Boiler  Mill G - setting packer plates
 Boiler Mill H - packer plates set
 Boiler east side (facing north)
 Boiler F11 & F10
 Boiler F8
Boiler ash hopper (SSC) 
 STH foundation and columns rebar work
 Central Electrical Building 
 New HV tower
STH Excavation works

13.04.2012

Boiler East - Civils preparing area for Steel erection

Ground being raised between Boiler F2 pedestals

                                       Boiler  F9 pedestals - formwork ready to be struck

Boiler F10 Rebar

 Boiler F8 Rebar

 Boiler Ash Hopper (SSC)

 Boiler F4 pedestals

 Mill H packing plates

 Mill G Scablling

 STH Formwork removal 

STH excavation works- south side

    STH Rebar works- west side

 New HV line - 1/5 tower erection

 SWFGD trench for GRP under new HV line

 Excavation and blinding works in MCW trench beneath New HV line

Central Electrical Building  foundations


12.04.2012

 Chimney-Steel Fixing Top Bar of the Base Foundation in Progress
  Chimney-Steel Fixing Top Bar of the Base Foundation in Progress
Fuel Gas Duct-Pipe Ducts-Preparation of  Bored Pile Surrounding Prior for Concreting
 F11-Boiler-Formworks Installation of Stumps in Progress
 F4-Boiler-Final Preparation of Stumps Prior for Concreting and Backfilling in Progress
  F9-Boiler Final Preparation of Stumps Prior for Concreting

GL BK-BM / GL B9-B12.5-Boiler- Backfilling in Progress
 Mill-South Side-Backfilling in Progress
Mill B-Mechanical-Scaffolding Erection in Progress
 Turbine Hall-West Side-Steel Fixing of Base Foundation in Progress
 Turbine Hall-North Side-Steel Fixing of Ground Walls in Progress
Turbine Hall-South Side-Excavation in Progress
 Central Electrical Building-GL A-G / GL 2- Final Preparation on Base Foundation Prior for Concreting in Progress
  Central Electrical Building-GL A-G / GL 3- Steel Fixing of Base Foundation in Progress

Boiler-East Side-Mechanical-Temporary Laydown Area for Boiler Steel Structure
 Phase 1-Main Cooling Water-Preparation Prior for Steel Fixing of Base Foundation in Progress
 Phase 1-Seawater Fuel Gas Desulfurization Glass Reinforced Pipes-2nd Layer-Backfilling and Compaction in Progress
 New HV Line-Pylons-Near Existing Switchyard-Steel Frame Erection in Progress
New HV Line-Pylons-Inside 25 year Ash Pond-Steel Fixing of Base Foundation in Progress