MJG4
26.08.2011
Excavation/Compaction -Turbine Hall -Preparation For Platform Level And Access Road Prior Commencement Of Bore Pile Works.
Bore Rig # 5 -Hr240 -Hydraulic Unit -Econpile.
Installation Of Steel Cage -Pile # B71 -1200mm dia.
Preparation Works -Bentonite Pipes To Turbine Hall -Synohydro.
Steel Reinforcement Preparation -Ground Beam -Consortium Office.
Formwork Preparation-Ground Beams -Consortium Office.
25.08.2011
Laying Of Bentonite Pipes -From Pond To Turbine Hall Area -Synohydro.
Installation/Setting Up Of Bore Rig # 5 -Hydraulic Unit.
Backfilling Works -MCWS -Pipes/Box Culvert Area.
Unloading Of Sheet Piles -For Bunker/Boiler/Turbine Hall -Prior De-Watering/Excavation For Foundation.
Excavation -Prior Commencement Of Bore Pile Works -Turbine Hall.
Survey /Setting Out Works -MCW -Pipes Area -Backfilling Works.
Ground Beam Preparation -Consortium Office.
25/08/11
400 tons of Sheet piles arrive for ST Foundation Cofferdam
24.08.2011
Excavation -Turbine Hall Area.
Bore Rig # 5 -Hydraulic -Pending Installation.
Backfilling -Circulation Water Pipes Area -BOP.
ALSTOM CABINS -4NOS.
23.08.2011
Soil Investigation -Coal Yard Area.
Preparation For Consortium Office -Ground Beams.
Concreting To Pile # A17-1200mm dia.
Installation -Steel Cage -Pile # A17-1200mm dia.
Installation -Steel Cage -Pile # A17 -1200mm dia.
22/08/2011
Site Dry Mix Batching Plant in full operation.
Site Office Foundation Ground Beams in progress.
22.08.2011
Concreting To Pile # B100 -1000mm dia.
Installation Of Bentonite Mixer Pumps -Synohydro.
Proposed Silt Trap Area.
Formwork -Ground Beams -Consortium Office.
Steel Fixing -Bore Pile Cage.
Installation Of Steel Cage -Pile # A23.
Boring To Pile # A29 -1000mm dia.
Installation Of Steel Cage -Pile # B100 -1000mm dia.
Ground Beam Preparations -Consortium Site Office.
Newer Posts
Older Posts
Home
Subscribe to:
Posts (Atom)