17.02.2012

F10-B4 -Boiler -West Side -Steel Fixing -Bottom Layer.

Mill-D -Hacking/Chipping -For Construction Joint.

Mill-D -Brushing /Cleaning Of Steel Reinforcement.

Bunker/Mill -Pedestal -B15-BB -Curing In Progress.

Mill-H -Installation Of Formwork.

Mill-H -Installation Of Formwork.

Turbine Hall -Condensate Sump Pit.

Turbine Hall -Grid -8 -Grid-9 -C/D -Preparation For Lean Concrete (-3.6MLSD).

Turbine Hall -Hacking Of Piles -Grid -6 -Grid -4 -B/D -(-3.6MLSD).

Boring To Pile #HN51-1200mm dia. -Chimney -BOP -EconPile.

PDA Test -Pile #A75-1000mm dia. -Absorber Foundation. -SinoHydro.

Concreting To Pile #HN51-1200mm dia. -Chimney -BOP -EconPile.

F4-Type D -Boiler -West Side -Final Inspection Prior Concreting.

16.02.2012

Boring To Pile #HN21-1200mm dia. -Chimney-BOP -EconPile.

FGD -Pipes Route -Soil Improvement -Spun Pile-600mm dia -Preparation Works.

Pile #A23-800mm dia -Absorber Foundation -Preparation For PDA Test.

Mill-H -Installation Of Formwork.

Turbine Hall -Condensate Sump Pit.

F1-Type-F -Boiler -West Side -Inspection Of Steel Reinforcement -Stump.

Bunker/Mill -Pedestal-B17/BB-Curing In Progress.

Bunker/Mill -Pedestal -B15/BB -Final Inspection Prior Concreting.

F3-Boiler -West Side -Stumps -Final Inspection Of Positioning & Elevation Prior Casting. F3-Boiler -West Side -Stump-Final Inspection Of Positioning Prior Concreting.

15.02.2012

Mill -H -Adjustment To Brickwall And Final Setting To J-Bolts.

Mill -D -Hacking /Chipping For Construction Joint.

Turbine Hall -(-3.6MLSD) -Preparation For Lean Concrete -Grid -4 -Grid 5 -B/D.

Turbine Hall-Condensate Sump Pit -Preparation For Installation Of I-Beam Support.

Turbine Hall -(-3.6MLSD) -Grid -5 - Grid -9 -B/D -Hacking Of Piles.

F4-Type D -Boiler -West Side -Formwork Installation Completed.

F6 -Stump -Boiler -West Side -Final Inspection To Elevation Prior Concreting.

F4-Type A -Boiler -West Side -Steel Reinforcement Completed.

F4-Type D -Boiler- West Side -Formwork Installation Completed.

Joint Inspection -Of Positioning & Elevation -F6 -Stumps -Boiler -West Side -Prior Concreting.

F10-B4 -Boiler -West Side -Steel Fixing -Bottom Layer.

B17-BB -Bunker/Mill -Pedestal -Final Checking Of Postioning And Elevation Prior Concreting.

14.02.2012

Mill-H -Adjusting And Leveling Of J-Bolts In Progress.

Mill-H -Setting And Leveling Of J-Bolts In Progress.

F3-Boiler -West Side -Stump -Inspection Of J-Bolts Positioning.

F3 -Boiler-West Side -Stump -Inspection Of J-Bolts Positioning.

Pile #HN18 -1200mm dia. -Installation Of Steel Cage -Chimney-BOP -SinoHydro.

Spun Piles-400mm dia. -FGD -Pipes -Soil Improvement.

Piling Rig -Preparation For 400mm dia. -Spun Pile -FGD -Pipes -Soil Improvement.

F4 -Type D -Boiler -West Side -Installation Of Formwork.

F11-B14 -Boiler -East Side -Final Inspection Prior Casting.

Turbine Hall -Level (-3.6MLSD).

Turbine Hall -Grid 9 -Grid 8 -B/D -(-3.6MLSD) -Carting Away Of Hacked Piles.

Turbine Hall -Grid 5 -Grid -4 -B/D -(-3.6MLSD) -Preparation For Lean Concrete.

F11 -B14 -Boiler -East Side -Concreting In Progress.

13.02.2012

F3 -Boiler -East Side -Steel Reinforcement-Stump- (Final Preparation) Prior Inspection.

F6 -Type A -Boiler -West Side -Curing In Progress.

Mill -C -Cleaning/Brushing To Steel Reinforcement.

F11-B14 -Boiler -East Side -Preparation For Steel Fixing -Stumps.

Mill -H -Adjusting/Leveling To J-Bolts In Progress -Prior Final Inspection.

Mill -H -Adjusting/Leveling To J-Bolts In Progress Prior Final Inspection.

Turbine Hall -Grid 9 -Grid 8 -B-D .

Mill -B -Brickwall Formwork In Progress.

F4-Type D -Boiler -West Side -Steel Reinforcement -Pile Caps.

Boring To Pile #HN53-1200mm dia. -Chimney -BOP -EconPile.

Preparation For Spun Pile 400mm dia. -Soil Improvement -FGD Pipes.

Pile #HN03-1200mm dia. -Chimney-Installation Of Steel Cage -SinoHydro.

Concreting To Pile #HN53-1200mm dia. -Chimney -BOP -EconPile.

F11-B14 -Boiler -East Side -Final Preparation Prior Casting.

Mill -D -Hacking/Chipping -Preparation For Construction Joint -2nd Stage Pour.

Turbine Hall -Excavation To Condensate Tank -Down To Level (-7.2MLSD).