Main Transformer No.1 Delivered for off loading on to foundation. - Looking NW |
| Boiler, FGD Ducts, Booster Fans and FF - Looking South |
| Boiler - Looking Southwest |
| Boiler - East Side |
| Boiler - 0m level |
| Boiler-Pressure Parts Wall and Pipe Headers |
| Boiler Area 2 Slab Concreting Works |
| Boiler - Looking Southeast |
| Steam Turbine Hall - Looking West |
| Steam Turbine Hall - Looking Northwest |
| Steam Turbine Hall-ST / GT Table - Looking North |
| Steam Turbine Hall - Looking East |
| Central Electrical Building - West Side |
| Central Electrical Building_MV Switchgear @ 4M Lvl |
| Central Electrical Building cable tray installation- 4m Level |
| Main Transformer Area- Looking East |
| Main Transformer Area - Main Transformer Rails |
| Main Transformer Area - Main Transformer Rails |
| Fabric Filter - Looking Northeast |
| SWFGD GRP Phase 3 and MCW Saddle |
| FGD Aeration Basin |
| MCW Pipe Trench at Reclaimed Existing 5 yr Ash pond |
| Service/Fire water storage tanks fdn works |
| Demin Water Treatment Plant Fdn Works |
| Screening House - Looking Southwest |
| Fly Ash Silo Fdn |
| Booster Fan, Absorbers and FGD Foundation - Looking South |