05.04.2012

Chimney-Steel Fixing Bottom Bars and Forworks Installation of Base Foundation in Progress
 F4-Boiler-Final Preparation of Base Foundation Prior for Concreting in Progress
 F1-Boiler-Casting Completed in Stumps and Removal of Formworks in Progress
 F9-Boiler-Final Preparation of Base Foundation Prior for Concreting in Progress
 F11-Boiler-Formworks Installation of Base Foundation in Progress
 F10-Boiler-Final Preparation of Stumps Prior for Concreting in Progress

F5-Boiler-Final Preparation of Base Foundation Prior for Lean Concreting in Progress 
 Mill G-Mechanical-Scaffolding Erection in Progress
Mill H-Mechanical-Preparation of Base Foundation for Pulverizer in Progress
 Turbine Hall-Base Raft Foundation Curing in Progress
  Turbine Hall-Base Raft Foundation Cover with Polystyrene for Insulataion
Turbine Hall-South Side Excavation in Progress
 Central Electrical Building- Steel Fixing of Base Foundation in Progress
  Central Electrical Building- Steel Fixing of Base Foundation in Progress
Phase 1-Main Cooling Water-Lean Concrete Casting Completed
 Phase 1- Fuel Gas Desulfurization Glass Reinforced Pipes-Backfilling in Progress
Boiler-Material Delivery-Main Column in Progress
Fuel Gas Duct-Duct Pipes-Hoisting of Bored Pile Steel Reinforcement in Progress