04.04.2012


APS, CMC and Mudajaya-Keep on Track for the Completion of Casting in the Turbine Hall Base Raft Foundation
 Turbine Hall-Casting Completed, Trowelling and Curing in Progress 
  Turbine Hall-Casting Completed, Trowelling and Curing in Progress 
 Turbine Hall-Casting Completed, Trowelling and Curing in Progress  
Turbine Hall-Hoisting of Polystyrene for the Surface Protection of Base Raft Foundation
 Chimney-Steel Fixing of Bottom Bars and Formworks Installation in Progress
 F10-Boiler-Final Preparation Prior for Concreting
 F11-Boiler-Formworks Installation Base Foundation in Progress 
  F9-Boiler-Final Preparation Prior for Concreting
  F4-Boiler-Final Preparation Prior for Concreting 
F4-Boiler-Steel Fixing of Stumps in Progress
 F1-Boiler-Final Preparation Prior for Concreting
 Mill E-Retaining Wall Formworks Installation in Progress
Mill C-Retaining Wall Formworks Installation in Progress
 Phase 1-Main Cooling Water-Preparation Prior for Lean Concreting
 Phase 1-Fuel Gas Desulfurization Glass Reinforced Pipes-Formation Level of Backfilling and Dewatering in Progress
 Turbine Hall-South Side-Box Tie in Progress
 Turbine Hall-South Side-Box Tie in Progress
Boiler-Mechanical-Boiler Main Steel Column Stock at East Side of the Boiler