06.04.2012

Chimney-Steel Fixing of Top Bars and Formworks Installation of Base Foundation in Progress
 F1-Boiler-Steel Fixing and Formworks Installation of Stumps in Progress
 F4-Boiler-Final Preparation of Base Foundation Prior for Concreting
 F9-Boiler-Casting Completed and Forworks Installation of Stumps in Progress
 F11-Boiler-Formworks Installation of Base Foundation in Progress
 F10-Boiler-Casting Completed and Removal of Formworks in Progress
Boiler Ash Pit- Formworks Installation 2nd Stage Perimeter Wall in Progress
 Mill H-  TNBJ Witnessing for the Setting up of the Packer Plate
 Mill B-Retaining Wall-Casting Completed and Curing in Progress
  Mill E-Retaining Wall-Casting Completed and Curing in Progress
 Mill A-Backfilling of South Side Area in Progress
Mill F-Mechanical-Scaffolding Erection in Progress

 Phase 1-Main Cooling Water-Excavation in Progress
Turbine Hall- Excavation of South Side Area in Progress