Chimney-Steel Fixing of Top Bars and Formworks Installation of Base Foundation in Progress
F1-Boiler-Steel Fixing and Formworks Installation of Stumps in ProgressF4-Boiler-Final Preparation of Base Foundation Prior for Concreting
F9-Boiler-Casting Completed and Forworks Installation of Stumps in Progress
F11-Boiler-Formworks Installation of Base Foundation in Progress
F10-Boiler-Casting Completed and Removal of Formworks in Progress
Boiler Ash Pit- Formworks Installation 2nd Stage Perimeter Wall in Progress
Mill H- TNBJ Witnessing for the Setting up of the Packer PlateMill B-Retaining Wall-Casting Completed and Curing in Progress
Mill E-Retaining Wall-Casting Completed and Curing in Progress
Mill A-Backfilling of South Side Area in Progress
Mill F-Mechanical-Scaffolding Erection in Progress
Phase 1-Main Cooling Water-Excavation in Progress
Turbine Hall- Excavation of South Side Area in Progress