21.03.2012

Chimney -Hacking Of Piles -Preparation For PIT & Steel Fixing -Foundation.

Fabric Filter -Formwork Installation -Stumps.

F1-Type A/B/C -Boiler -West Side -Formwork Installation.

F2-Type F -Type C -Boiler -East Side -Steel Fixing -Beam.

F11-B10/B12 -Preparation For Lean Concrete.

F10-B8/B6 -Excavation In Progress.

Mill-B -Installation Of J-Bolts.

F9 -Boiler -East Side -Excavation In Progress.

Erection Of Site Office -EverShendai.

Chimney -Steel Fixing -Bottom Layer -Base Foundation.

Chimney -Steel Fixing -Bottom Layer -Base Slab In Progress.

F11-B12/B10 -Boiler -East Side -Lean Concreting In Progress.

Mill-C -Final Preparation Prior Concreting.

F10-B8/B6 -Boiler -West Side -Preparation For Lean Concrete.