17.03.2012

FGD -Pipes -Spun Pile 400mm dia -Soil Improvement.

Chimney -Hacking Of Piles In Progress.

Bar Bending Yard -Chimney.

F4 -Boiler -East Side -Excavation In Progress.

Joint Survey Inspection -J-Bolts -Prior Concreting -Mill-D.

Waste Water Pit -Final Inspection -Prior Concreting -Base Slab.

Mill -C -Formwork Installation In Progress.

Turbine Hall -Steel Fixing -Raft Foundation.

F4-Boiler -East Side -Lean Concrete Completed.