19.03.2012

Chimney -Hacking Of Piles In Progress.

Bar Bending Yard -Chimney.

Formwork Preparation -Chimney -Foundation.

Fabric Filter -Installation Of Formwork -Stumps.

F1-Type A/B/C -Boiler -West Side -Steel Fixing -Pile Cap / Beams.

Waste Water Pit Base Slab -Curing In Progress.

Mill-C -Steel Fixing -Cantilever Slab.

F5-Boiler -PIT In Progress Prior Steel Fixing.

Turbine Hall -Steel Reinforcement -Raft Foundation -Top Layer.

Turbine Hall -Steel Fixing -Raft Foundation.

Fabric Filter -Backfilling & Compaction -Grid 5 -Grid 8.

F4-Boiler -West Side -Inspection Of Steel Reinforcement Prior Shuttering.

Mill-C -Installation Of I-Beams & J-Bolts Frame.

Erection Of Site Office -EverShendai.