Chimney -Pile Hacking In Progress.
Chimney -Bar Bending Yard For Foundation & Base Slab.
Fabric Filter -Formwork Installation -Stumps.
Waste Water Pit -Base Slab -Curing In Progress.
F10-B10/B12 -Boiler -West Side -Excavation In Progress.
Mill-C -Steel Fixing -Cantilever -Slab.
Mill-B -Installation Of J-Bolts.
Turbine Hall -Steel Reinforcement -Top Layer -Raft Foundation.
Turbine Hall -Steel Reinforcement -Raft Foundation -Top Layer.
FGD -Pipes -1st Phase -Area-1 -Sheet Piles -Preparation For Excavation & Pile Cutting.
Condensate Sump Pit -Preparation For 1st Stage Pour -Pipe Casing.
Turbine Hall -Inspection -Steel Reinforcement -Raft Foundation -Top Layer.