18.01.2012

Excavation -Preparation For F4 -Foundation -Type A & D-Boiler.

Sheet Piling -Coffer Dam -F1 -Foundation -Type A/B/C -Boiler -West Side.

F1 -Boiler -West Side -Backfilling & Compaction -9th Layer.

Mill -D -Brickwall Formwork In Progress.

Bunker/Mill -B1-B3 -BA/BB -Curing In Progress.

Turbine Hall -Excavation -2nd Stage (South/East Side) .

Turbine Hall -Excavated Area -2nd -Stage -(-2.1MLSD).

PDA -CWP -Turbine Hall -Pile # QA19 -BOP.

F3 -Boiler -East Side -Inspection -Steel Reinforcement -Top Layer.

F3 -Boiler -East Side -Inspection -Steel Reinforcement -Top Layer.

Boring To Pile #HN07 -1200mm dia. -Chimney -BOP -EconPile.

Concreting To Pile #A92-800mm dia. -Absorbers Foundation -SinoHydro.