Concreting To Pile #A70-1000mm dia. -Absorbers Foundation -SinoHydro.
Bunker/Mill -B5 -BB -Steel Fixing In Progress.
Turbine Hall -Excavation -2nd Stage -Down To Level -2.1MLSD.
Bunker/Mill -B5-BA -Installation Of Steel Reinforcement -Stump.
F3 -Boiler -East Side -Steel Reinforcement -Top Layer.
F7 -Boiler -East Side -Concreting In Progress.
Installation Of Steel Cage -Pile #A36-800mm dia. -Absorbers Foundation -EconPile.
F7 -Boiler -East Side -Concreting In Progress.
F2 Foundation Type F -Boiler -East Side -Preparation For Lean Concrete.
Hacking Of Piles -Ash Hopper.
Pile #A36-800mm dia. -Absorbers Foundation -Installation Of Vermiculite & Plug.
Concreting To Pile #A36-800mm dia. -Absorbers Foundation -EconPile.