16.01.2012

Boring To Pile #HN23 -1200mm dia. -Chimney -BOP -EconPile.

F2 -Foundation -Type F -Hacking Of Piles (10nos.) In Progress.

F7 -Boiler -East Side -Curing In Progress.

Mill -G -Brickwall Formwork In Progress.

Turbine Hall -Excavation -2nd Stage -(-2.1MLSD) -In Progress.

Mill -E -Steel Fixing -2nd Stage In Progress.

Installation Of Steel Cage -Pile #A07 -800mm dia. -Absorbers Foundation -SinoHydro.

Bunker/Mill -B1-B3 -BB -BA -Curing In Progress.

Concreting To Pile #HN23 -1200mm dia. -Chimney -BOP.

F4 Foundation -Type-E -Excavtion In Progress. -Boiler -.

Bunker/Mill -B11 -Compaction In Progress.

Turbine Hall -Excavation-2nd Stage In Progress (-2.1MLSD).