Boring To Pile #HN23 -1200mm dia. -Chimney -BOP -EconPile.
F2 -Foundation -Type F -Hacking Of Piles (10nos.) In Progress.
F7 -Boiler -East Side -Curing In Progress.
Mill -G -Brickwall Formwork In Progress.
Turbine Hall -Excavation -2nd Stage -(-2.1MLSD) -In Progress.
Mill -E -Steel Fixing -2nd Stage In Progress.
Installation Of Steel Cage -Pile #A07 -800mm dia. -Absorbers Foundation -SinoHydro.
Bunker/Mill -B1-B3 -BB -BA -Curing In Progress.
Concreting To Pile #HN23 -1200mm dia. -Chimney -BOP.
F4 Foundation -Type-E -Excavtion In Progress. -Boiler -.
Bunker/Mill -B11 -Compaction In Progress.
Turbine Hall -Excavation-2nd Stage In Progress (-2.1MLSD).