17.01.2012

Bunker/Mill -B1-B3 -BA/BB -Curing In Progress.

Mill -E -Compaction-4th Layer In Progress.

Mill -E -Steel Fixing -2nd Stage.

FDT -Mill -D -FDT -4th Layer In Progress.

Installation -Steel Cage -Pile #HN52-1200mm dia. -Chimney -BOP.

PIT -Ash Hopper.

Concreting To Pile #HN52-1200mm dia. -Chimney -BOP -EconPile.

Concreting To Pile #A32-800mm dia-Absorbers Foundation -SinoHydro.

Sheet Piling -Coffer Dam -F4 -Type -E -Foundation -Boiler.

F2 -Type A &B -Boiler East Side -Steel Fixing -Pile Caps & Tie Beams.