03.01.2012

Weekly EHS -Management Walk Down.-Alstom/TNBJ/OE/CMC/MCB.

Bunker/Mill -B9 -BA -BB -Scheduled For Concreting On 05.01.2012.@ 300m3.

Bunker/Mill -Installation Of Steel Reinforcement -B7-BA.

Bunker/Mill -Type 2 Foundation -B3-BA.

Consortium Office -Alstom.

Consortium Office -Alstom -1st Floor.

Consortium Office -Alstom-1st Floor -Painting Of Gypsum Board In Progress.

Consortium Office -Alstom -1st Floor -Painting Of Gypsum Board In Progress.

Consortium Office -Alstom -1st Floor -Painting Of Gypsum Board Ongoing.

Production Of Pre-Cast Box Culvert -Water Intake -BOP -Murray Robert.

Production Of Pre-Cast Box Culvert -Water Intake -BOP -Murray Robert.

Production Of Pre-Cast Box Culvert -BOP -Murray Robert.

BOP -Water Intake -Sheet Piling In Progress -BOP -Murray Robert.

F6 -Boiler -West Side -FDT In Progress.

F3/F6 -Boiler -West Side -Compaction -Preparation For FDT.

Pile #A45 -800mm dia -Absorbers Foundation -Installation Of Steel Cages -EconPile.

F3/F6 -Boiler -West Side -Compaction In Progress.

F1 -Boiler -West Side -Inspection Of Re-Bar Bottom Layer.