04.01.2012

Boring To Pile #A49-800mm dia. -Absorber Foundation -EconPile.

Fabric Filter -Formwork Installation -Tie Beams.

Crushing Of Piles -F1 -EconPile.

F1 -Foundation -Boiler -East Side -Steel Reinforcement -Top Layer.

F3/F6 -Boiler -West Side -Removing Of Sheet piles (Coffer Dam).

F3/F6 -Boiler East Side -Inspection Of Pile Heads Preparation.

Pile #A49-800mm dia. -Absorber Foundation -Installation Of Steel Cage -EconPile.

Boring To Pile #A87-1000mm dia. -Absorber Foundation -EconPile.

BOP -MCWS -Preparation To Commence With Piling Works -Spun Pile -600mm dia.

BOP -MCWS -Preparation To Commence With Piling Works -Spun Pile 600mm dia.

BOP -MCWS -Backfilling In Progress.