Fabric Filter -Final Preparation Prior Concreting -Scheduled On 10.01.2012 @ 120m3.
F2 -Boiler -East Side -Preparation For Backfilling Works.
Sheet Piling -Coffer Dam -F2-Type 2F -Foundation -Boiler -East Side.
F3 -Boiler -East Side -Hacking Of Piles & Carting Away Of Debris (Hacked Piles).
Bunker/Mill -B11 -B7 -BA/BB -Curing In Progress.
Bunker/Mill -B11-B7 -BA/BB -Curing In Progress.
Bunker/Mill -B5 -B1 -BB -Installation Of Formwork In Progress.
Turbine Hall -Excavation-1st Stage In Progress.
Turbine Hall -Excavation -1st Stage In Progress.
Boring To Pile #A74-1000mm dia. -Absorbers Foundation -EconPile.
Concreting To Pile #A50-800mm dia. -Absorbers Foundation -EconPile.
Consortium Office -Alstom.
F1 -Boiler -West Side -Final Preparation Prior Concreting.
F1 -Boiler -West Side -Final Preparation Prior Concreting.