Boring To Pile #A46 -800mm dia. -Absorber Foundation -EconPile.

Fabric Filter -Scheduled For Concreting -Grid 1 -Grid 3 @ 100m3 On 07.01.12.

F1 -Boiler -East Side -Steel Reinforcement Completed.

F2 -Boiler -East Side -Preparation For Backfilling Works.

F7 -Boiler -East Side -Carting Away Of Hacked Piles.

F3-Boiler -East Side -Hacking Of Piles.

Bunker/Mill -Backfilling & Compaction -5th Layer -B17.

Backfilling & Compaction 5th Layer -Bunker/Mill -B17.

Final Inspection Prior Concreting -Bunker/Mill -B11 -B7 -BA/BB.

Concreting -Bunker/Mill -B11 -B7 -BA/BB @ 330m3.

Concreting To Pile #A66 -1000mm dia. -Absorber Foundation -EconPile.

Fabric Filter -Inspection Of Re-Bar Prior Shuttering Works -Grid 1 -Grid 3.

Fabric Filter -Grid -1 -Grid-3 -Inspection Of Re-Bar Prior Shuttering Works.

F1 -Boiler -West Side -Installation Of Formwork.

F1 -Boiler -West Side -Inspection Of Re-Bar Prior Shuttering Works.



F1 -Boiler -West Side -Steel Reinforcement Completed.