Boring To Pile #A46 -800mm dia. -Absorber Foundation -EconPile.
Fabric Filter -Scheduled For Concreting -Grid 1 -Grid 3 @ 100m3 On 07.01.12.
F1 -Boiler -East Side -Steel Reinforcement Completed.
F2 -Boiler -East Side -Preparation For Backfilling Works.
F7 -Boiler -East Side -Carting Away Of Hacked Piles.
F3-Boiler -East Side -Hacking Of Piles.
Bunker/Mill -Backfilling & Compaction -5th Layer -B17.
Backfilling & Compaction 5th Layer -Bunker/Mill -B17.
Final Inspection Prior Concreting -Bunker/Mill -B11 -B7 -BA/BB.
Concreting -Bunker/Mill -B11 -B7 -BA/BB @ 330m3.
Concreting To Pile #A66 -1000mm dia. -Absorber Foundation -EconPile.
Fabric Filter -Inspection Of Re-Bar Prior Shuttering Works -Grid 1 -Grid 3.
Fabric Filter -Grid -1 -Grid-3 -Inspection Of Re-Bar Prior Shuttering Works.
F1 -Boiler -West Side -Installation Of Formwork.
F1 -Boiler -West Side -Inspection Of Re-Bar Prior Shuttering Works.
F1 -Boiler -West Side -Steel Reinforcement Completed.