F2 -Boiler -East Side -Curing In Progress.
F1 -Boiler -East Side -Steel Fixing Ongoing.
F6 -Boiler -West Side -Backfilling & Compaction In Progress.
F3/F6 -Boiler -West Side -Backfilling & Compaction In Progress.
Bunker/Mill -B9 -BB-Installation Of Formwork.
Bunker/Mill -B7-BA -Steel Fixing In Progress.
Turbine Hall -Excavation 1st Phase In Progress.
Turbine Hall -Excavation 1st Phase In Progress.
Turbine Hall -Excavation -1st Phase In Progress.
Concreting To Pile #QA47 -1000mm dia. -CWP -BOP -SinoHydro.
F6 -Boiler -East Side- Hacking Of Piles Ongoing.
F2 -Boiler- East Side.
Crushing Of Cut Piles -EconPile -F1 Foundation -Boiler -West side.
BOP -CMC/MCB -Sub-Station -Project Power Supply -Base Slab Preparation.
No comments:
Post a Comment