Fabric Filter -Steel Fixing -Tie Beam.
Carting Away Of Debris -(Hacked Piles) -F1 Foundation -Boiler -West Side.
F3 -Boiler -East Side- Preparation For Lean Concrete.
F3 -Boiler -East Side. -Preparation For Lean Concrete.
Bunker/Mill -B9 -BA/BB.
Bunker/Mill -B9 -B7 -BA -Installation Of Formwork.
Bar Cutting & Bending Yard -Bunker/Mill.
Turbine Hall -Excavation -1st Phase In Progress.
Turbine Hall -Excavation 1st Phase In Progress.
BOP -MCWS -Backfilling In Progress.
BOP-MCWS -Preparation To Commence With Piling Works -Spun Pile.
BOP -MCWS -Backfilling In Progress.
BOP -MCWS -Preparation To Commence With Spun Pile.