Consortium Office -Alstom.
Weekly -EHS -Tool Box Meeting.
Consortium Office -Alstom -Grd.Floor.
Consortium Office -Alstom -Grd. Floor.
Fabric Filter -Steel Fixing -Tie Beams.
F2 -East Side -Installation Of Formwork -Scheduled For Concreting On 30.12.11 @75m3.
F3-Boiler -East Side -Preparation For Lean Concreting.
F1 -Boiler -West Side- Hacking Of Piles (10-nos) Ongoing.
F3/F6 -Boiler -West Side -Backfilling & Compaction Ongoing.
F3/F6 -Boiler -West Side -Bakfilling /Compaction In Progress.
Bunker/Mill -B9 -B7 -BA -Steel Fixing.
Curing -Bunker/Mill -B17 -B13 -Type 2/Type 3/Type 3A/Tie Beams -BA/BB.
Fabric Filter -Steel Reinforcement -Tie Beams.
F6 -Boiler -East Side -Lean Concreting.