F10-B4 -Boiler -West Side -Hacking Of Piles In Progress (12nos).
F6 -Boiler -West Side -Steel Fixing -Stump.
F6-Type A -Boiler -West Side -Ready For Concreting.
F11-B14 -Boiler -East Side -Inspection Of Steel Reinforcement -Bottom Layer.
F11-B14 -Boiler -East Side -Steel Reinforcement.
F11 -B14 -Boiler -East Side -Inspection Of Steel Reinforcement -Bottom & Top Layer.
Mill -H -Final Setting To J-Bolts Prior Inspection.
Turbine Hall -Sheet Piling -Condensate Sump Pit.
F3 -Boiler -West Side -Inspection of Steel Reinforcement -Stump.
Turbine Hall -Lean Concrete Preparation -Grid 8 -Grid -7 -B/D.(-3.6MLSD).
Turbine Hall -Condensate Sump Pit -Excavation In Progress -Down To Level (-7.2MLSD).
F4 -Type-A -Boiler -West Side -Steel Fixing In Progress.