16.02.2012

Boring To Pile #HN21-1200mm dia. -Chimney-BOP -EconPile.

FGD -Pipes Route -Soil Improvement -Spun Pile-600mm dia -Preparation Works.

Pile #A23-800mm dia -Absorber Foundation -Preparation For PDA Test.

Mill-H -Installation Of Formwork.

Turbine Hall -Condensate Sump Pit.

F1-Type-F -Boiler -West Side -Inspection Of Steel Reinforcement -Stump.

Bunker/Mill -Pedestal-B17/BB-Curing In Progress.

Bunker/Mill -Pedestal -B15/BB -Final Inspection Prior Concreting.

F3-Boiler -West Side -Stumps -Final Inspection Of Positioning & Elevation Prior Casting. F3-Boiler -West Side -Stump-Final Inspection Of Positioning Prior Concreting.