17.02.2012

F10-B4 -Boiler -West Side -Steel Fixing -Bottom Layer.

Mill-D -Hacking/Chipping -For Construction Joint.

Mill-D -Brushing /Cleaning Of Steel Reinforcement.

Bunker/Mill -Pedestal -B15-BB -Curing In Progress.

Mill-H -Installation Of Formwork.

Mill-H -Installation Of Formwork.

Turbine Hall -Condensate Sump Pit.

Turbine Hall -Grid -8 -Grid-9 -C/D -Preparation For Lean Concrete (-3.6MLSD).

Turbine Hall -Hacking Of Piles -Grid -6 -Grid -4 -B/D -(-3.6MLSD).

Boring To Pile #HN51-1200mm dia. -Chimney -BOP -EconPile.

PDA Test -Pile #A75-1000mm dia. -Absorber Foundation. -SinoHydro.

Concreting To Pile #HN51-1200mm dia. -Chimney -BOP -EconPile.

F4-Type D -Boiler -West Side -Final Inspection Prior Concreting.