F4 -Type A -Boiler -East Side -Steel Fixing In Progress.
F6 -Type A -Boiler -East Side -Final Preparation Prior Concreting.
F10-B4 -Boiler -East Side -Hacking Of Piles (12nos) In Progress.
F1-B4 -Boiler -West Side -Curing In Progress.
Mill -H -Preparation To Install J-Bolts.
F11-B14 -Boiler -East Side -Steel Reinforcements -Top Layer.
Turbine Hall -Sheet Piling To Condensate Sump Pit In Progress.
Mill -H -Pedestal -Installation Of J-Bolts In Progress.
Mill-H -Installation Of J-Bolts In Progress.
Mill-H -Installation Of -J-Bolts In Progress -8nos.
Turbine Hall -Excavation -3rd Stage -Down To Level (-3.6MLSD).
Turbine Hall -Gridline 8 -Gridline 6 -B/D -Preparation For Lean Concrete -(-3.6MLSD).