08.02.2012

Final Inspection -F1-B4 -Boiler -West Side -Prior Concreting.

F4-Type-A -Boiler -Steel Fixing In Progress.

F4 -Type-A -Boiler -Steel Fixing In Progress.

Pre-Inspection -Steel Reinforcements -Stump -F3-Foundation -Boiler -West Side.

Pre-Inspection -J-Bolts -Stump -F6 -Foundation -Boiler -West Side.

F6 -Type A -Boiler -West Side -Final Preparation Prior Casting.

F10-B14 -Steel Fixing -Bottom Layer In Progress.

Turbine Hall -Preparation For 3rd Stage Excavation -Down To Level (-3.6MLSD).

Turbine Hall -Grid -8 -Grid -9 -B/D -Preparation For Lean Concrete (-3.6MLSD).

Boring To Pile#HN54 -1200mm dia. -Chimney -BOP -EconPile.

Boring To Pile #HN44-1200mm dia. -Chimney -BOP -SinoHydro.

Concreting To Pile #HN54-1200mm dia. -Chimney -BOP -EconPile.

F1-B4 -Boiler -West Side -Concreting In Progress.

F11 -B4 -Boiler -West Side -Lean Concreting In Progress.