Boring To Pile #HN25 -1200mm dia. -Chimney -BOP -EconPile.
F2-Type-F -Boiler -East Side -Curing In Progress.
F4-Type E -Boiler -Curing In Progress.
F4-Type-D -Preparation For Pile Hacking.
F4-Type A -Boiler -West Side -Hacking Of Piles Completed.
Hacking Of Piles -F4 -Type D -Boiler -West Side.
F11-B14 -Boiler -East Side -Steel Fixing -Bottom Layer.
Turbine Hall -Preparation For 3rd Stage Excavation (-3.6MLSD).
Turbine Hall -Preparation For 3rd Stage Excavation -(-3.6MLSD).
Turbine Hall -Installation Of I-Beam -Support (Bracing) To Sheet Piles -(Coffer Dam) -South.
Turbine Hall -Installation Of I-Beam Support (Bracing) To Sheet Piles -(Coffer Dam)-South.