Installation Of Steel Cage -Pile #B16-800mm dia. -Booster Fan -SinoHydro.

Fabric Filter -Steel Fixing & Formwork Installation -Grid 6 -Grid 8.

F2 -Type -F -Boiler -East Side -Formwork Installation Completed.

F4 -Type E -Foundation -Boiler -Preparation For Formwork Installation.

F11 Foundation -Boiler -Preparation For Lean Concreting.

F7 -Boiler -East Side- Steel Fixing -Stump.

Steel Fixing -Mill -G -Final Stage Pour.

Brickwall Formwork -Mill -D.

CEB -Lean Concrete Completed -Gridline -2.

CEB -Preparation For Lean Concrete.

Turbine Hall -Excavation -2nd Stage (-2.1MLSD) -South/West Side.

F1-Foundation -Boiler -West Side- Cleaning (Hacked Piles) .

PIT -F1 -Foundation -Boiler -West Side.

F2 Foundation-Type F -Boiler -East Side -Steel Fixing -Stump In Progress.