Fabric Filter -Final Preparation Prior Concreting -Gridline 6 -Gridline 8.
F11 -Foundation -Boiler -Hacking Of Piles In Progress.
Boring To Pile #HN49-1200mm dia. -Chimney -BOP -EconPile.
F2-Foundation -Type A/B/C -Boiler -East Side -Formwork Installation In Progress.
F2-Foundation -Type-F -Boiler -East Side -Curing In Progress.
F2-Foundation -Type F -Boiler -East Side -Curing In Progress.
Mill -C -Brickwall Formwork In Progress.
Dismantling Of Sheet Piles (Coffer Dam) -F3/F7 -Boiler -East Side.
F3/F7 -Boiler -East Side -Compaction -In Progress (7th Layer).
F2-Foundation -Type-F -Boiler -East Side -Curing In Progress.
Boring To Pile#HN43-1200mm dia. -Chimney -BOP -SinoHydro.
Concreting To Pile #HN49-1200mm dia. -Chimney -BOP -EconPile.