01.02.2012

Boring To Pile #HN48-1200mm dia. -Chimney -BOP -EconPile.

Boring To Pile #B03-800mm dia. -Booster Fan -SinoHydro.

F2 -Foundation -Type A/B/C -Boiler -East Side -Steel Fixing -Tie Beams In Progress.

Mill -H -J-Bolts Frame -Setting Up In Progress.
F11-Foundation -Boiler -Hacking Of Piles (12 nos).

Steel Cage Installation -Pile #HN48-1200mm dia. -Chimney -BOP -EconPile.

Concreting -Pile #B03 -800mm dia. -Booster Fan -SinoHydro.

F2-Type A/B/C -Boiler -East Side -Steel Fixing -Tie Beam In Progress.

F3-Boiler -East Side -Compaction (Backfilling Works) In Progress.(4th Layer).

F2-Type-F -Boiler -East Side -Final Inspection Prior Concreting.